Import procedure guide for used machinery exceeding ordinary age criteria but requested for import to maintain production and business operations

Used machinery · Article 9 · Production continuity

IMPORT PROCEDURE GUIDE FOR USED MACHINERY EXCEEDING ORDINARY AGE CRITERIA BUT REQUESTED FOR PRODUCTION CONTINUITY

Used machinery that exceeds the ordinary age criteria is not a routine import case. The shipment may be held if the enterprise applies the wrong HS Code (classification code under the Harmonized System), treats Article 9 as a substitute for all specialized policies, fails to prove remaining capacity/performance of at least 85%, fails to prove consumption not exceeding 15% above design, submits an inspection certificate beyond 06 months, or cannot explain why the machine is necessary to maintain production and business operations in Vietnam. These errors may cause customs delay, document supplementation, loss of C/O preference, administrative exposure, unplanned DEM/DET and unresolved post-clearance obligations. This guide provides an E2E (End-to-End) map for enterprises to review before ETA (Estimated Time of Arrival), including HS, duty, Article 9 dossier, specialized policy, customs documents, clearance workflow and pre-arrival risk controls.

Products covered by Import procedure guide for used machinery exceeding ordinary age criteria but requested for import to maintain production and business operations at an import inspection area
Illustration of the product group and document review before customs clearance.

QUICK FACTS

ItemQuick review content
Product scopeUsed machinery/equipment whose equipment age exceeds the ordinary age criteria under clause 1 Article 6 of Decision 18/2019/QD-TTg, but the enterprise producing in Vietnam requests import to maintain production/business operations.
Core thresholdRemaining capacity/performance must reach at least 85% of design capacity/performance, and consumption of raw materials, materials and energy must not exceed 15% compared with design.
HS basisThere is no single HS code for this case. The machine must still be classified by actual function, structure and operating principle, normally under Chapter 84 or 85.
Core dossierApplication letter under current Form No. 01, stamped copy of enterprise registration certificate, inspection certificate issued by a designated/recognized inspection body, explanation for production continuity and approval document of the Ministry of Science and Technology.
Key timingInspection certificate for used machinery/equipment is acceptable only when issued not more than 06 months before the machinery arrives at a Vietnamese border gate.
Legal cautionThis case does not automatically apply to used technological lines, Group 2 goods, sector-regulated machinery, temporary import/re-export, repair/warranty goods, samples, or goods not imported for production use in Vietnam.

SCOPE OF APPLICATION

This guide applies to single used machinery/equipment under Chapter 84 or 85 that has been assembled and operated after manufacture, exceeds ordinary age criteria, and is requested for import because the enterprise must maintain production/business operations in Vietnam.

  • Do not combine this case with used technological lines; technological lines have separate criteria and dossiers.
  • Do not apply it to machinery in banned import lists, Group 2 goods, or machinery governed by separate sector regulations without separate review.
  • New goods, refurbished goods, warranty goods, temporary import/re-export, EPE/FDI/factory imports and project goods may trigger different policy layers.
  • Attached modules, software, wireless functions, encryption/security, batteries, adapters, chargers, electrical cabinets or spare parts must be reviewed separately.
  • Where data is insufficient, state: Review is required based on catalogue, datasheet, model and actual import purpose.

CLASSIFICATION & TECHNICAL IDENTIFICATION

The importer must identify the machine through catalogue, datasheet, nameplate, model, serial, year of manufacture, function, structure, operating principle, processed material, production stage, accessories and condition. Generic descriptions such as “used machine” or “production machine” may result in incorrect HS, incorrect Article 9 dossier, missing specialized policy and inconsistent customs documents.

TECHNICAL IDENTIFICATION CRITERIA

Criteria to checkDocuments to compareRisk if described incorrectlySuggested description on documents/declaration
Machine name and main functionCatalogue, datasheet, nameplate, overall photos, operation videoGeneric wording may lead to wrong HS, wrong Decision 18 analysis and weak inspection dossierUsed [machine name], model…, serial…, for [manufacturing process]
Equipment ageYear of manufacture on nameplate, inspection certificate, manufacturer confirmation if anyUnclear whether the machine exceeds ordinary age criteria; wrong Article 6/Article 9 routeYear of manufacture…, year of import…, used machinery exceeding ordinary age criteria
Remaining capacity/performanceInspection certificate, test run, design specifications, actual outputFailure to prove the 85% threshold may lead to refusalRemaining capacity/performance …% of design capacity/performance
Raw material/material/energy consumptionInspection report, power/utility consumption records, technical manualFailure to prove consumption not exceeding 15% above designConsumption compared with design: …%
Operating/maintenance conditionInspection report, maintenance records, color photos, test-run videoCertificate may be insufficient under Article 10; machine may be suspected obsolete or poor qualityUsed machine in operating condition, maintained according to…
Safety, energy-saving and environmental standardsRelevant QCVN/TCVN or G7/Korea standards, test report, declaration if anyFailure to prove compliance with clause 2 Article 6 and Article 10Manufactured/evaluated according to… standard
Single machine or technological lineLayout, process flow, packing list, contractConfusing single machine with a technological line leads to wrong criteria and procedureSingle used machine / part of line / complete used technological line
Accessories/modulesAccessory list, electrical diagram, battery/power module specificationAccessories may trigger quality inspection, energy efficiency, ICT/security or sector policyMain machine with accessories listed separately if needed

HS CODE – DUTY – C/O

Article 9 is only a permission-review mechanism for used machinery exceeding age criteria. It does not create a separate HS code. HS must still be determined by function, structure, operating principle and actual use. C/O should only be requested after HS and product description have been finalized.

Reference HS groupApplication conditionRisk if incorrectDocuments to compare
84.xxMechanical machinery, production machines, processing machines, packaging machines, material handling or industrial equipment with mechanical functionWrong Chapter 84/85 affects duty, C/O and Decision 18 scopeCatalogue, operating principle, function, process flow, technical manual
85.xxElectrical machinery/equipment, motors, controllers, electrical cabinets, electric heating equipment or primarily electrical machinesConfusion between mechanical and electrical machinery; possible omission of energy/specialized policyElectrical diagram, power rating, datasheet, nameplate
8422Washing/filling/sealing/packaging machinery where packing is the main functionGeneric production-machine declaration may misstate HS and C/OPackaging function, speed, packaging type, model list
8477Rubber/plastics processing machinery where the processed material and process match the headingConfusion with metalworking or packaging machineryProcessed material, screw/barrel, mold/clamping data, process description
8456–8463Machine tools for cutting, turning, milling, grinding, pressing, bending or forming metal depending on processWrong HS by machining principle, CNC control or processed materialTooling data, CNC control, working envelope, process photos
8419 / 8514Industrial thermal treatment equipment/furnaces, depending on heat source and electric mechanismWrong distinction between thermal and electrical equipment; missing safety/energy reviewHeating method, temperature range, chamber size, energy source

REFERENCE TAX REVIEW TABLE

Tax itemHow to determineReference noteRisk point
MFN import dutyAccording to the final HS code in the current tariff scheduleNo common rate; Chapter 84/85 industrial machines may range from 0% to 20% or more depending on the final HSWrong HS changes the entire duty and C/O assessment
Ordinary import dutyAccording to the ordinary tariff or the applicable rule at declaration dateMay be 150% of MFN if no separate ordinary rate is provided; must be checked at declaration dateReference wording must not replace current tariff lookup
VATAccording to VAT policy at import dateUsually 10%, unless current tax instruments provide otherwiseDo not confuse import-duty preference with VAT treatment
Special preferential duty under C/OAccording to the applicable FTA and valid C/O formMay be 0% or lower than MFN depending on FTA/HS; check the FTA scheduleWrong C/O form, origin criterion, goods description or HS may invalidate preference

APPLICABLE SPECIALIZED POLICY

Goods scenarioPossible policyDocuments to checkAuthority / portal if identifiableRecommended timingRisk note
Used machinery exceeding age criteria while the enterprise is producing in VietnamArticle 9 Decision 18/2019/QD-TTg; as amended by Decision 02/2026/QD-TTg, use current form and timelineForm No. 01 application, stamped enterprise registration certificate, inspection certificate, production-continuity explanationMinistry of Science and Technology; online public service portal if availableBefore booking or before ETADo not wait until cargo arrival to request approval
Machinery satisfying ordinary Article 6 criteriaUsed-machinery import dossier under Decision 18/Decision 28, not Article 9 routeManufacturer confirmation or inspection certificate as applicableCustoms office; designated/recognized inspection bodyBefore ETADo not confuse Article 6 and Article 9
Group 2 goods or sector-regulated machineryDecision 18 does not apply where the machine is Group 2 or already governed by sector regulations; follow sector rulesGroup 2 list, QCVN/TCVN, permits, conformity, inspection records if anySector ministry, Customs, NSW if applicableBefore contract finalizationDo not rely on Decision 18 when a sector regulation governs the goods
Machine with electrical modules, control cabinet, motor, battery, adapter or chargerMay trigger energy efficiency, electrical safety, battery, labeling or other sector policiesModule datasheet, electrical diagram, battery spec, model listCustoms and relevant specialized authorityBefore ETAAccessories may change the dossier
FDI/EPE/factory import for production continuityBesides Decision 18, review import rights, use purpose, fixed asset treatment, investment project and customs regimeERC/IRC, contract, PO, investment file, production/BOM documentsCustoms authority, MOST, investment authority if neededBefore contract signingWrong import purpose or customs regime may create post-clearance risk
Sample/warranty/temporary import-re-export goodsMay fall outside the production-use import route under Decision 18Warranty contract, temporary import dossier, purpose letter, serial listCustomsBefore declarationDo not use Article 9 for goods not imported for production use in Vietnam

LEGAL DOCUMENTS TO REVIEW

Document groupDocument name/numberIssuing authorityEffective timingRole in procedureKey articles/appendicesReview note
DecisionDecision 18/2019/QD-TTgPrime MinisterIssued 19 Apr 2019, effective 15 Jun 2019Core regulation on import of used machinery, equipment and technological linesArticles 1, 4, 6, 9, 10, 11, Appendices I/IIRead together with Decision 28/2022 and Decision 02/2026
Amending DecisionDecision 28/2022/QD-TTgPrime MinisterEffective 01 Mar 2023Amends several provisions of Decision 18Article 1 and amended provisionsDo not apply separately from Decision 18
2026 Amending DecisionDecision 02/2026/QD-TTgPrime MinisterEffective 08 Jan 2026Amends point b clause 2 Article 9, shortens consultation timeline under point c clause 3 Article 9 to 05 working days, and replaces the application formArticle 2, Appendix Form No. 01Use for Article 9 dossiers after its effective date
Foreign tradeLaw on Foreign Trade Management 2017; Decree 69/2018/ND-CPNational Assembly/GovernmentDecree 69 effective 15 May 2018Framework for banned goods, temporary import/re-export and conditional importLists and foreign-trade management rulesCheck where the machine falls under banned/sector-regulated goods
CustomsCustoms Law 2014; Decree 08/2015/ND-CP and amendmentsNational Assembly/GovernmentApply at declaration dateCustoms dossier, preservation pending documents, document/physical inspectionCustoms dossier, channeling and post-clearance rulesCheck current customs instruments
TariffDecree 26/2023/ND-CP, Decree 199/2025/ND-CP and relevant FTA tariff schedulesGovernmentApply by periodBasis for MFN, ordinary duty, VAT and special preferential dutyChapter 84/85 by final HSNo single duty rate applies to all over-age machinery
StandardsRelevant QCVN/TCVN or G7/Korea standards for the actual machineRelevant issuing authorityBy each standardBasis for safety, energy-saving and environmental evaluation in the inspection certificateClause 2 Article 6; points d/g clause 1 Article 10 of Decision 18Select standards by machine type

VIEW / DOWNLOAD ORIGINAL LEGAL TEXTS

Enterprises should additionally verify the documents on official legal document portals or websites of issuing authorities before applying them.

CUSTOMS CLEARANCE DOCUMENT SET

Commercial documents
  • Commercial Invoice
  • Packing List
  • Bill of Lading/Air Waybill
  • Sales Contract/Purchase Order
  • C/O if preferential duty is claimed
  • Catalogue/datasheet, machine photos, original nameplate, model/serial list
Article 9 dossier
  • Application letter under current Form No. 01
  • Production-continuity explanation and use plan
  • Stamped copy of enterprise registration certificate
  • Inspection certificate issued by a designated/recognized body
  • Approval document of the Ministry of Science and Technology
Technical / sector dossier
  • Relevant QCVN/TCVN/G7/Korea standard
  • Test run, maintenance record, operation video
  • Group 2, conformity, inspection or energy-efficiency dossier if applicable
  • Nameplate / labeling dossier
  • Environmental and energy-saving documents if applicable

OPERATIONAL DOSSIER CHECKLIST

File groupRequired documentsUsed forUsually prepared byCommon errorPre-ETA check
Article 9 applicationForm No. 01 application, production-continuity explanation, use plan and necessity in the production processRequest approval before customs clearanceLegal/Compliance/FactoryGeneric explanation without production impactLink the machine with process, output, downtime and production plan
Enterprise legal fileStamped enterprise registration certificate; investment/factory documents if needed to prove production in VietnamProve the enterprise is producing in VietnamLegal/AdminBusiness scope/factory address inconsistent with dossierMatch ERC/IRC, factory address, business line and production process
Inspection certificateCertificate from designated/recognized body; Article 10 contents including 85%, 15%, standards, operating condition and color photosCore evidence for Article 9 conditionsQA/Engineering/Supplier/Inspection bodyMissing model/serial/photos/standards or certificate over 06 monthsReview template before inspection and check Article 10 items
CommercialInvoice, Packing List, Sales Contract/PO, B/L/AWB, C/O if claimedCustoms declaration and tax calculationProcurement/Docs/LogisticsMachine name differs from model, year, serial or originMatch documents with nameplate and inspection certificate
TechnicalCatalogue/datasheet, nameplate, photos/video, manual, layout, process flowHS, policy, inspection and Article 9 explanationEngineering/Factory/SupplierInsufficient basis for function or equipment agePrepare model–serial–year–function–HS matrix
Sector policy if anyConformity, safety inspection, energy efficiency, permit, Group 2 dossier if applicableHandle policy outside Decision 18Compliance/QAAssuming Article 9 replaces all other permitsMap policy by machine/module before ETA

Control principle: Goods name, quantity, model, serial, origin, technical specifications, year of manufacture, standard and operating condition must match 100% across commercial documents, catalogue, nameplate, inspection certificate, approval dossier and customs declaration.

DECISION POINTS THAT MAY HOLD THE SHIPMENT

Decision pointQuestion to answerEvidenceConsequence if unclearRecommended handling
Correct Article 9 scopeIs the enterprise producing in Vietnam and importing the machine to maintain production?ERC/IRC, production plan, process flow, explanationMOST may not approveProve the production stage affected without the machine
Over-age but still efficientDoes the machine meet 85% performance and 15% consumption thresholds?Inspection certificate, test run, design dataArticle 9 condition not satisfiedArrange inspection before shipment if possible
HS basisIs the machine under Chapter 84/85 or another sector regime?Catalogue, datasheet, principle of operationWrong duty, wrong policy and rejected C/OFinalize HS before C/O and declaration
Certificate validityWill the used-machine inspection certificate exceed 06 months by arrival date?Inspection certificate, ETA, B/L/AWBRe-inspection or rejectionPlan inspection timeline backward from ETA
MOST approvalHas the Ministry of Science and Technology issued approval before clearance?Approval document, submitted dossierIncomplete customs dossier for Article 9Submit early, do not wait for port arrival
Other specialized policyDoes the machine trigger Group 2, energy, safety inspection, ICT/security or environmental policy?QCVN/TCVN, Group 2 list, module listMissing permit or post-clearance obligationReview policy for each model and accessory

PRACTICAL E2E WORKFLOW

Pre-ETA review.

Confirm Article 9 scope, HS, Decision 18/28/02 policy, duty, C/O, nameplate, certificate validity and any sector policy.

Lock documents and technical files.

Finalize Invoice, Packing List, B/L/AWB, catalogue/datasheet, model/serial list, nameplate photos, year of manufacture, standards and inspection scope.

Prepare Article 9 approval dossier.

Submit Form No. 01 application, stamped enterprise registration certificate, inspection certificate and production-continuity explanation to the Ministry of Science and Technology. Late submission after ETA may hold the shipment.

Lodge customs declaration.

Green channel: system clearance subject to conditions. Yellow channel: document check. Red channel: document and physical inspection. Common questions include value, HS, model, year, C/O, inspection certificate and approval document.

Clear, deliver and complete post-clearance obligations.

Move goods to factory/warehouse, complete labeling/conformity/safety inspection if applicable, archive the batch dossier and prepare explanations for post-clearance audit.

PRE-ETA RISK CHECKLIST

RiskConsequencePre-ETA preventionDocuments to check
Production-continuity need not provenWeak Article 9 dossier and prolonged reviewPrepare process explanation, output impact, downtime and why replacement is necessaryApplication letter, production process, maintenance plan
Inspection certificate lacks 85%/15% dataApproval condition not satisfiedAgree inspection scope before inspecting the machineDraft certificate, Article 10, datasheet
Inspection certificate older than 06 months at arrivalRe-inspection or dossier rejectionPlan inspection–ETD–ETA–submission timelineInspection date, ETA, B/L/AWB
Single machine confused with technological lineWrong dossier, criteria and procedureSeparate single machine / part of line / complete line in contract and packingContract, packing list, layout
C/O shows wrong HS or descriptionSpecial preferential duty deniedRequest C/O only after HS and machine name are finalizedC/O, invoice, packing list, catalogue
Machine is subject to separate sector policyArticle 9 alone cannot clear all policy obligationsReview Group 2, energy efficiency, occupational safety and environmental policy by modelSector list, QCVN, test report

FAQ

QuestionShort answer
Can over-age used machinery still be imported?Yes, Article 9 provides a review mechanism if the enterprise is producing in Vietnam, needs the machine to maintain production, the machine retains at least 85% capacity/performance and consumption does not exceed 15% above design.
Is approval from the Ministry of Science and Technology required?Yes. For Article 9, the approval document from the Ministry of Science and Technology is required in addition to the customs dossier.
How long is the inspection certificate valid?For single used machinery/equipment, it is accepted only when not more than 06 months from issuance to arrival at the Vietnamese border gate.
Does Article 9 replace other permits or specialized inspection?No. If the machine is Group 2 or sector-regulated, the relevant specialized policy must still be reviewed.
Can C/O reduce duty?Potentially, if C/O form, origin criterion, goods description, HS and direct transport comply with the relevant FTA.
Are samples, warranty goods or temporary import treated the same?Not automatically. These cases may fall outside Decision 18 or outside Article 9 and must be reviewed by import purpose.
What if invoice model differs from catalogue/nameplate?Correct the dossier before ETA. Model/serial discrepancies can weaken HS, inspection and Article 9 approval.
Can the machine be brought to storage while awaiting documents?This depends on customs rules and the specific missing document. Do not assume storage release is available without checking the current customs basis.

TGIMEX IMPLEMENTATION SUPPORT

This guide provides a map for HS, tax, dossier and specialized policy for over-age used machinery requested for production continuity. In real shipments, enterprises still need to review catalogue, datasheet, model, documents, origin and import purpose.

Operational capability signals

Agent network in more than 60 countries; membership in WCA, WCA China Global, VLA, HNLA; capability in sea, air, road/rail freight, customs clearance, C/O, permits, warehousing and domestic delivery.

Pre-ETA review

Review HS, Decision 18/28/02 policy, C/O, duty, labeling, catalogue, datasheet, model, serial and inspection certificate.

Compliance dossier control

Cross-check Invoice, Packing List, B/L/AWB, C/O, catalogue, inspection certificate, nameplate and technical documents.

International logistics

Coordinate overseas agents, carriers/airlines, ETA, pre-alert and transport documents.

Customs declaration

Prepare declaration dossier, handle Green/Yellow/Red channels and support explanations on HS, value, origin and specialized policy.

Post-clearance

Archive dossier by shipment, review labels, conformity, safety inspection or energy labeling where applicable.

For shipments likely to trigger specialized inspection, permits, C/O or labeling requirements, enterprises should not wait until cargo arrival to review documents. A small discrepancy among Invoice, Packing List, catalogue, datasheet, C/O or label may cause document supplementation, clearance delay or unplanned storage costs. TGIMEX supports an E2E import plan: pre-ETA policy review, document control, international freight coordination, customs declaration, clearance handling, domestic delivery and post-clearance recordkeeping.

QUICK CONSULTATION

NEED TO REVIEW IMPORT PROCEDURES OR A SHIPPING PLAN?

Send us the product name, shipping route, current dossier, or implementation request in advance so we can suggest a suitable approach that is practical, focused, and aligned with your shipment.

CALL NOW
Zalo
HOTLINE 0963 856 664 / 0982 135 393
EMAIL info@tgimex.com
SUITABLE FOR International shipping · Customs procedures · Import licenses · B2B logistics

Leave a Reply

Discover more from TGIMEX VIETNAM JSC

Subscribe now to keep reading and get access to the full archive.

Continue reading